第1题
Project team building is most difficult in which type of environment?
A . weak matrix organization
B . strong matrix organization
C . projectized organization
D . functional organization
E . expediter organization
第2题
108 In which type of organization is team building likely to be most difficult?
A. Functional
B. Projectized
C. Matrixed
D. Project expediter
E. Project coordinator
第3题
In which type of organization is team building likely to be most difficult?
A . Functional
B . Projectized
C . Matrixed
D . Project expediter
E . Project coordinator
第4题
A.at one’s wits end
B.in his wits end
C.at his wits’ end
D.out of his wits end
第5题
A.drawn
B.to drawing
C.to draw
D.drew
第6题
A.analyzed
B.estimate
C.made
D.received
第7题
104 In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
A. Not working directly with the assigned functional employees
B. Employees spend only a short amount of time assigned to the project
C. Not being knowledgeable enough to evaluate employees on technical judgment
D. All of the above
E. A and B only
第8题
A.felt obliging to
B.feel obliged to
C.find it easily to
D.found it very difficult to
第9题
第10题
The reason that cost management is so difficult in project management is that:
A . Projects by definition and nature are non-recurring events and are therefore difficult to predict.
B . There are no tools for identifying project tasks.
C . Project managers do not care about tracking costs, as only schedules are important to all project managers.
D . A and B only
E . B and C only
第11题
190 In which type of organization is team building likely to be most difficult?
A. Functional
B. Projectized
C. Matrixed
D. Project expediter
E. Project coordinator