92The main player in project communication is the A.sponsor B.project manager C.functional
92 The main player in project communication is the
A. sponsor
B. project manager
C. functional manager
D. functional team
E. All of the above
92 The main player in project communication is the
A. sponsor
B. project manager
C. functional manager
D. functional team
E. All of the above
第1题
The main player in project communication is the
A sponsor
B project manager
C functional manager
D functional team
E All of the above.
第2题
174 The main player in project communication is the
A. sponsor
B. project manager
C. functional manager
D. functional team
E. All of the above
第3题
92 The most common form. of organizational communication is
A. Upward to management
B. Downward to subordinates
C. Horizontal to peers
D. Horizontal to customers
E. All of the above
第4题
92 The project charter is developed by:
A. senior management
B. the customer
C. the project manager
D. both A and C
E. None of the above
第5题
92 The highest degrees of project risk and uncertainty are associated with the following phase of the project:
A. conceptual
B. execution
C. cut-over
'D. post project evaluation
E. A and D only
第6题
92 The ability to reduce risk is _____ to how far you have progressed through the project life cycle. A. inversely proportional
B. directly proportional
C. not related
D. the responsibility of the risk executive
E. is directly proportional to the amount at stake